Pandemic hits KCC social housing building programme

Jan 12, 2021 08:25 By radiokerrynews
Pandemic hits KCC social housing building programme
Share this article

240 local authority houses are currently under construction in Kerry. The houses are across ten estates throughout the county as well as four single rural

240 local authority houses are currently under construction in Kerry.

The houses are across ten estates throughout the county as well as four single rural houses.

Kerry County Council says the pandemic had a significant impact on its social housing delivery programme as construction was suspended for a time.

Advertisement

Projects due by the end of 2020 have been delayed into the new year.

Thirty houses being built by Kerry County Council, including 28 in Balloonagh Tralee and two single rural dwellings in Glenbeigh, were due for completion in 2020.

Eight two-bed apartments in Listowel were also due for delivery.

Advertisement

Seven social housing units were given to Kerry County Council in 2020 by developers as part of planning obligations in Barraduff, Dingle and Killarney.

Subject to the pandemic, the council plans to deliver 119 housing units by the end of 2021 in Ardfert, Rathmore, Ballybunion, Lixnaw, Kenmare, Tralee, Killarney, Beaufort and Caragh Lake.

A further 105 units will be completed by approved housing bodies by the end of 2021.

Advertisement

 

Share this article
Advertisement

RadioKerry Newsletter

Sign up now to keep up to date with the latest news.

Processing your request...

You are subscribed now! please check your email to confirm your subscription.